Progress is steadily being made
to improve to South Stanley Park as agreed upon by the Niagara
Neighbourhood community in consultation with myself and Parks staff.
The work on the Pool House is underway and is proceeding in two Phases with completion by the year's end:
The construction work for Stanley Outdoor Pool Phase I is in progress on site, and is scheduled to be completed prior to the pool opening in June.
The work being done under Phase I includes:
1) the original CAMP state-of-good-repair work which included replacing the windows, doors, and replacing various finishes, and
2) preliminary work to prepare for the
renovation/accommodation of a the multi-purpose space, including selective
demoliton, reconfiguring the storage areas, construction of selected new
partition walls, and the completion of a barrier free washroom.
Currently, the demolition is in progress.
The construction work for Stanley Outdoor Pool Phase II is scheduled to start in September after the pool shuts down for the season, and will be completed by year end.
The work being done under Phase II
includes completing the new multi-purpose area, adding a vestibule, heating the
building so that it can be used year round, and insulating the building.
There will be further updates on implementing the Plans for the rest of the Park in the next month.